Transportation system
One of the basical demands for customer serving is total service from mixing step, asphalt concrete stock to product delivery based on customer demand.
|
Transportation capacity of BMT: 3,000Tons/day
BMT truck is in operation for dayly: 30 trucks with 750Tons/cycle
BMT could demand in days: 10 trucks with 250Tons/cycle
BMT could demand in 2 days: 10 trucks with 250Tons/cycle
Distance from Mixing plant of BMT to the construction site
60 minutes: inside districts, Dist. 2, Dist. 9, Thu Duc Dist., Dist. 7, Nha Be Dist., Binh Chanh Dist., Binh Tan Dist., Binh Duong Province.
90 minutes: Cu Chi Dist., Hoc Mon Dist., Long An Province, Dong Nai Province.
120 minutes: Tien Giang , Ba Ria – Vung Tau, Tay Ninh, Binh Phuoc province
Mixing plant capacity: 300 Tons/h = 3,000 Tons per day
Real capacity of pavement machine: 100 Tons/h
Operation capacity of customer: 500 Tons/day
Time for get the product from silos: 1 minutes
Time for cover and get ticket: 5 minutes
Time for transportation to construction site: 60, 90, 120 minutes
Time for waiting for the pavement machine: 20 minutes
Time for paving work: 15 minutes
Time for return to the Mixing plant: 60, 90, 120 minutes
Total time: 161, 191, 221 minutes
Last time to construction site: 11pm, 11.30pm, 12.00pm
In order to satisfy the demand time: based on the distance of customers’ construction site, BMT can use over 20 trucks for customer satisfaction.